DEFIANCE COUNTY ENGINEER
Power Dam Rd Tire Shred Embankment
Bid Date: 5/12/2022
Engineer's Estimate: $440,000.00
GEDDIS PAVING RENSI DIRT WORKS RG ZACHRICH
TOLEDO, OH DEFIANCE, OH DEFIANCE, OH
UNIT TOTAL UNIT TOTAL UNIT TOTAL
Item Description Quantity Units PRICE COST PRICE COST PRICE COST
202 Pavement Removed, As Per Plan 4222 SY    $                      -      $                      -    $        5.50  $            23,221.00
203 Excavation  2,168 CY    $                      -      $                      -    $        5.10  $            11,056.80
203 Embankment 8593 CY    $                      -      $                      -    $       13.56  $          116,521.08
203 Embankment TS, As Per Plan 1500 CY    $                      -      $                      -    $       30.00  $            45,000.00
Special Tire Shred Delivery 300 Tons    $                      -      $                      -    $      (16.00)  $            (4,800.00)
203 Embankment #89, As Per Plan 1200 Tons    $                      -      $                      -    $       40.00  $            48,000.00
Special Spreading Recycled Materials 4855 SY    $                      -      $                      -    $        1.50  $             7,282.50
206 Cement Stabilized Subgrade, 12" Deep 4855 SY    $                      -      $                      -    $        1.30  $             6,311.50
206 Cement 152 Tons    $                      -      $                      -    $     235.00  $            35,720.00
Special High Strength Woven Polypropylene Fabric 11,237 SY    $                      -      $                      -    $        2.87  $            32,250.19
704 Standard Concrete Masonry Block 14,309 Each    $                      -      $                      -   3.3  $            47,219.70
606 Gaurdrail, Type MGS 1000 Feet    $                      -      $                      -    $       28.40  $            28,400.00
614 Maintaining Traffic 1 Lump    $                      -      $                      -    $  9,000.00  $             9,000.00
624 Mobilization 1 Lump    $                      -      $                      -    $ 38,000.00  $            38,000.00
        Total  NO BID  Total  NO BID  Total  $       443,182.77