DEFIANCE COUNTY ENGINEER
 
2023 PAVEMENT MARKING
Bid Date:   3/30/2023
The Aero-Mark Co. LLC Ogelsby Construction, Inc.
Streetsboro, OH Norwalk, OH
        UNIT TOTAL UNIT TOTAL
ITEM DESCRIPTION QTY.   COST COST COST COST
643 Stop Line 34 Ea.  $   209.00  $         7,106.00  $   195.00  $             6,630.00
               
643 RR Symbol Mkg. 0 Ea.  $   500.00  $                     -    $   820.00  $                         -  
               
643 Word on Pavement "SCHOOL"  1 Ea.  $   500.00  $            500.00  $   855.00  $                855.00
               
643 Center Line 41.1 Mile  $   395.00  $       16,234.50  $   330.00  $          13,563.00
               
643 Center Line (<500') 3.5 Mile  $   750.00  $         2,625.00  $   790.00  $             2,765.00
               
643 White Edge Line 82.2 Mile  $   388.00  $       31,893.60  $   297.00  $          24,413.40
               
643 White Edge Line (<500') 6 Mile  $   750.00  $         4,500.00  $   790.00  $             4,740.00
               
643 Polyester Material  1,830 Gal.  $      41.70  $       76,311.00  $     45.75  $          83,722.50
643 Spotting Centerline 25.99 Mile  $      80.00  $         2,079.20  $     66.00  $             1,715.34
624 Mobilization 2 Ea.  $1,600.00  $         3,200.00  $1,435.00  $             2,870.00
       
643 No Passing Zone Study 0 Mile  $   300.00  $                     -   650.00  $                         -  
643 No Passing Zone Study 0 Mile    $                     -      $                         -  
   $ 144,449.30    $    141,274.24