| DEFIANCE COUNTY ENGINEER | |||||
| CR 122/CR 134 | |||||
| Bid Date: | 3/21/2024 | ||||
| Engineer's Estimate: | $1,400,000.00 | ||||
| Gerken Paving, Inc | |||||
| Napoleon, OH | |||||
| UNIT | TOTAL | ||||
| Item | Description | Quantity | Units | PRICE | COST | 
| 202 | Pavement Removed | 2131 | SY | $ 13.00 | $ 27,703.00 | 
| 407 | Tack Coat | 15070 | Gal | $ 2.50 | $ 37,675.00 | 
| 411 | Stabilized Crushed Aggregate, As Per Plan | 3497 | Tons | $ 36.50 | $ 127,640.50 | 
| 441 | Asphalt Concrete Surface Course Type 1 (449) PG58-22, As Per Plan | 12583 | Tons | $ 96.00 | $ 1,207,968.00 | 
| 643 | Edge Line | 22.52 | Mi | $ 1,312.00 | $ 29,546.24 | 
| 643 | Center Line | 11.23 | Mi | $ 1,276.00 | $ 14,329.48 | 
| 643 | Stop Line | 84 | Feet | $ 50.00 | $ 4,200.00 | 
| 643 | Railroad Symbol Marking | 2 | Each | $ 1,355.00 | $ 2,710.00 | 
| 604 | Monument Box (Adjusted to Grade) | 8 | Each | $ 915.00 | $ 7,320.00 | 
| Special | Formed Construction Joint | 23 | Each | $ 790.00 | $ 18,170.00 | 
| 614 | Maintaining Traffic | 1 | Lump | $ 14,000.00 | $ 14,000.00 | 
| 624 | Mobilization | 1 | Lump | $ 34,000.00 | $ 34,000.00 | 
| Total | $ 1,525,262.22 | ||||