| DEFIANCE COUNTY ENGINEER | |||||||||||||||||||||
| EVANSPORT SIDEWALKS | |||||||||||||||||||||
| Bid Date: | 8/4/2025 | ||||||||||||||||||||
| Engineer's Estimate: | $426,000.00 | ||||||||||||||||||||
| Ward Construction | RG Zachrich Construction | Advanced Excavation | Smith Paving | Fenson Contracting | |||||||||||||||||
| Leipsic, OH | Defiance, OH | McComb, OH | Norwalk, OH | Fort Jennings, OH | |||||||||||||||||
| UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | ||||||||||||
| Item | Description | Qty | Units | PRICE | COST | PRICE | COST | PRICE | COST | PRICE | COST | PRICE | COST | ||||||||
| 608 | 4" Concrete Sidewalk | 24414 | SF | $ 8.30 | $ 202,636.20 | $ 6.50 | $ 158,691.00 | $ 6.50 | $ 158,691.00 | $ - | $ - | $ 6.60 | $ 161,132.40 | ||||||||
| 304 | 4" Aggregate Base | 356 | CY | $ 120.00 | $ 42,720.00 | $ 140.00 | $ 49,840.00 | $ 110.00 | $ 39,160.00 | $ - | $ - | $ 100.00 | $ 35,600.00 | ||||||||
| 204 | Subgrade Compaction | 3201 | SY | $ 1.00 | $ 3,201.00 | $ 1.50 | $ 4,801.50 | $ 0.65 | $ 2,080.65 | $ - | $ - | $ 1.00 | $ 3,201.00 | ||||||||
| 712 | Detectable Warning | 88 | SF | $ 50.00 | $ 4,400.00 | $ 60.00 | $ 5,280.00 | $ 75.00 | $ 6,600.00 | $ - | $ - | $ 50.00 | $ 4,400.00 | ||||||||
| 202 | Concrete Removed | 1586 | SY | $ 11.00 | $ 17,446.00 | $ 12.00 | $ 19,032.00 | $ 16.00 | $ 25,376.00 | $ - | $ - | $ 30.00 | $ 47,580.00 | ||||||||
| Special | Sidewalk Matched, as Per Plan | 27 | SY | $ 92.00 | $ 2,484.00 | $ 27.50 | $ 742.50 | $ 227.00 | $ 6,129.00 | $ - | $ - | $ 60.00 | $ 1,620.00 | ||||||||
| 452 | 6" Non-Reinforced Concrete Pavement | 351 | SY | $ 80.00 | $ 28,080.00 | $ 68.50 | $ 24,043.50 | $ 105.00 | $ 36,855.00 | $ - | $ - | $ 75.00 | $ 26,325.00 | ||||||||
| 411 | 4" Stabilized Crushed Aggregate (Base) | 47 | CY | $ 150.00 | $ 7,050.00 | $ 140.00 | $ 6,580.00 | $ 95.00 | $ 4,465.00 | $ - | $ - | $ 100.00 | $ 4,700.00 | ||||||||
| 202 | Concrete Removed | 207 | SY | $ 43.00 | $ 8,901.00 | $ 12.00 | $ 2,484.00 | $ 50.00 | $ 10,350.00 | $ - | $ - | $ 30.00 | $ 6,210.00 | ||||||||
| 611 | 12" Conduit, Type C | 318 | LF | $ 56.00 | $ 17,808.00 | $ 85.00 | $ 27,030.00 | $ 65.00 | $ 20,670.00 | $ - | $ - | $ 48.00 | $ 15,264.00 | ||||||||
| 611 | 12" Conduit Grate, as Per Plan | 4 | EA | $ 120.00 | $ 480.00 | $ 400.00 | $ 1,600.00 | $ 500.00 | $ 2,000.00 | $ - | $ - | $ 400.00 | $ 1,600.00 | ||||||||
| 611 | 12" Conduit Tee | 1 | EA | $ 400.00 | $ 400.00 | $ 250.00 | $ 250.00 | $ 575.00 | $ 575.00 | $ - | $ - | $ 335.00 | $ 335.00 | ||||||||
| 611 | 12" Conduit Elbow | 3 | EA | $ 300.00 | $ 900.00 | $ 450.00 | $ 1,350.00 | $ 550.00 | $ 1,650.00 | $ - | $ - | $ 250.00 | $ 750.00 | ||||||||
| 202 | Catch Basin Removed, as Per Plan | 2 | EA | $ 300.00 | $ 600.00 | $ 1,000.00 | $ 2,000.00 | $ 1,500.00 | $ 3,000.00 | $ - | $ - | $ 2,075.00 | $ 4,150.00 | ||||||||
| 659 | 4" Topsoil | 194 | CY | $ 90.00 | $ 17,460.00 | $ 84.00 | $ 16,296.00 | $ 63.00 | $ 12,222.00 | $ - | $ - | $ 85.00 | $ 16,490.00 | ||||||||
| 670 | Slope Erosion Protection | 1742 | SY | $ 2.25 | $ 3,919.50 | $ 2.22 | $ 3,867.24 | $ 2.25 | $ 3,919.50 | $ - | $ - | $ 2.40 | $ 4,180.80 | ||||||||
| 832 | Erosion Control | 1 | EA | $ 1.00 | $ 1.00 | $ 3,000.00 | $ 3,000.00 | $ 3,500.00 | $ 3,500.00 | $ - | $ - | $ 1,000.00 | $ 1,000.00 | ||||||||
| 832 | Storm Water Pollution Prevention Plan | 1 | LUMP | $ 2,125.00 | $ 2,125.00 | $ 2,500.00 | $ 2,500.00 | $ 2,125.00 | $ 2,125.00 | $ - | $ - | $ 1,200.00 | $ 1,200.00 | ||||||||
| 832 | Storm Water Pollution Prevention Inspections | 1 | LUMP | $ 6,120.00 | $ 6,120.00 | $ 4,000.00 | $ 4,000.00 | $ 2,000.00 | $ 2,000.00 | $ - | $ - | $ 2,500.00 | $ 2,500.00 | ||||||||
| 832 | Storm Water Pollution Prevention Inspection Software | 1 | LUMP | $ 890.00 | $ 890.00 | $ 2,500.00 | $ 2,500.00 | $ 2,100.00 | $ 2,100.00 | $ - | $ - | $ 4,000.00 | $ 4,000.00 | ||||||||
| 201 | 18" Tree Removed | 6 | EA | $ 500.00 | $ 3,000.00 | $ 510.00 | $ 3,060.00 | $ 1,000.00 | $ 6,000.00 | $ - | $ - | $ 950.00 | $ 5,700.00 | ||||||||
| 201 | 30" Tree Removed | 1 | EA | $ 1,250.00 | $ 1,250.00 | $ 1,200.00 | $ 1,200.00 | $ 1,000.00 | $ 1,000.00 | $ - | $ - | $ 1,050.00 | $ 1,050.00 | ||||||||
| 201 | 48" Tree Removed | 1 | EA | $ 3,700.00 | $ 3,700.00 | $ 3,700.00 | $ 3,700.00 | $ 2,000.00 | $ 2,000.00 | $ - | $ - | $ 1,250.00 | $ 1,250.00 | ||||||||
| 201 | 18" Stump Removed | 1 | EA | $ 50.00 | $ 50.00 | $ 50.00 | $ 50.00 | $ 500.00 | $ 500.00 | $ - | $ - | $ 500.00 | $ 500.00 | ||||||||
| 201 | 30" Stump Removed | 2 | EA | $ 100.00 | $ 200.00 | $ 100.00 | $ 200.00 | $ 500.00 | $ 1,000.00 | $ - | $ - | $ 550.00 | $ 1,100.00 | ||||||||
| 201 | 48" Stump Removed | 2 | EA | $ 100.00 | $ 200.00 | $ 100.00 | $ 200.00 | $ 750.00 | $ 1,500.00 | $ - | $ - | $ 600.00 | $ 1,200.00 | ||||||||
| 201 | 60" Stump Removed | 1 | EA | $ 100.00 | $ 100.00 | $ 100.00 | $ 100.00 | $ 1,500.00 | $ 1,500.00 | $ - | $ - | $ 650.00 | $ 650.00 | ||||||||
| Special | Sign Remove and Replace | 2 | EA | $ 150.00 | $ 300.00 | $ 500.00 | $ 1,000.00 | $ 100.00 | $ 200.00 | $ - | $ - | $ 50.00 | $ 100.00 | ||||||||
| 301 | Clearing and Grubbing | 1 | LUMP | $ 10,000.00 | $ 10,000.00 | $ 6,000.00 | $ 6,000.00 | $ 4,000.00 | $ 4,000.00 | $ - | $ - | $ 3,500.00 | $ 3,500.00 | ||||||||
| 203 | Excavation | 781 | CY | $ 33.00 | $ 25,773.00 | $ 60.00 | $ 46,860.00 | $ 31.00 | $ 24,211.00 | $ - | $ - | $ 50.00 | $ 39,050.00 | ||||||||
| 203 | Embankment | 32 | CY | $ 33.00 | $ 1,056.00 | $ 60.00 | $ 1,920.00 | $ 25.00 | $ 800.00 | $ - | $ - | $ 25.00 | $ 800.00 | ||||||||
| 659 | Seeding and Mulching | 1465 | SY | $ 1.80 | $ 2,637.00 | $ 1.80 | $ 2,637.00 | $ 1.80 | $ 2,637.00 | $ - | $ - | $ 4.00 | $ 5,860.00 | ||||||||
| 624 | Mobilization | 1 | Lump | $ 16,500.00 | $ 16,500.00 | $ 63,000.00 | $ 63,000.00 | $ 65,000.00 | $ 65,000.00 | $ - | $ - | $ 65,000.00 | $ 65,000.00 | ||||||||
| Total | $ 432,387.70 | Total | $ 465,814.74 | Total | $ 453,816.15 | Total | NO BID | Total | $ 467,998.20 | ||||||||||||