Bid Date: 2/23/2023
Engineer's Estimate: $1,450,000.00
RG Zachrich Constr. Miller Bros Const. Vernon Nagel Rietschlin Const.        
Defiance OH Archbold OH Napoleon, OH Crestline, OH         
UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL                
Item Description Quantity Units PRICE COST PRICE COST PRICE COST PRICE COST                        
202 Pavement Removed, As Per Plan 1480 Sq. Yd.  $          6.00  $             8,880.00  $          6.00  $             8,880.00  $         10.00  $            14,800.00  $           -    $                      -  
202 Guardrail Removed 465 LF  $          7.00  $             3,255.00  $          7.00  $             3,255.00  $           5.00  $             2,325.00  $           -    $                      -  
203 Excavation  3,491 CY  $          5.00  $            17,455.00  $          9.00  $            31,419.00  $         12.00  $            41,892.00  $           -    $                      -  
203 Embankment 3,159 CY  $        10.00  $            31,590.00  $          9.00  $            28,431.00  $         12.00  $            37,908.00  $           -    $                      -  
203 Embankment TS, As Per Plan 366 CY  $        36.00  $            13,176.00  $        63.00  $            23,058.00  $         33.00  $            12,078.00  $           -    $                      -  
203 Embankment #89, As Per Plan 476 Tons  $        44.00  $            20,944.00  $        49.00  $            23,324.00  $         45.00  $            21,420.00  $           -    $                      -  
Special Repurposed Bridge Beams 3780 SF  $        23.00  $            86,940.00  $        14.00  $            52,920.00  $         20.00  $            75,600.00  $           -    $                      -  
Special High Strength Woven Polyproylene fabric 2195 SY  $          3.64  $             7,989.80  $          4.50  $             9,877.50  $           4.00  $             8,780.00  $           -    $                      -  
Special Spreading Recycled Materials 1704 SY  $          9.70  $            16,528.80  $        14.00  $            23,856.00  $         12.00  $            20,448.00  $           -    $                      -  
206 Cement Stabilized Subgrade, 16" Deep 1704 SY  $          3.31  $             5,640.24  $        15.00  $            25,560.00  $         12.00  $            20,448.00  $           -    $                      -  
206 Cement  60 Tons  $      310.00  $            18,600.00  $      220.00  $            13,200.00  $       225.00  $            13,500.00  $           -    $                      -  
304 12" Aggregate Base (Drives) 62 Tons  $        76.00  $             4,712.00  $        49.00  $             3,038.00  $         70.00  $             4,340.00  $           -    $                      -  
407 Tack Coat 189 Gal  $          1.00  $                189.00  $          2.50  $                472.50  $           2.50  $                472.50  $           -    $                      -  
823 Asphalt Concrete Surface Course Type 1 (449) PG64-22, As Per Plan 131 Ton  $      154.00  $            20,174.00  $      120.00  $            15,720.00  $       120.00  $            15,720.00  $           -    $                      -  
441 Asphalt Concrete Intermediate Course Type 2 (449) PG64-22, As Per Plan 184 Tons  $      128.00  $            23,552.00  $      110.00  $            20,240.00  $       110.00  $            20,240.00  $           -    $                      -  
605 Aggregate Drains 280 LF  $          6.50  $             1,820.00  $        17.00  $             4,760.00  $         20.00  $             5,600.00  $           -    $                      -  
606 Guardrail, Type MGS  612.5 Feet  $        22.00  $            13,475.00  $        21.00  $            12,862.50  $         21.00  $            12,862.50  $           -    $                      -  
606 Guardrail, Type MGS 25' Radius 37.5 Feet  $        22.00  $                825.00  $        21.00  $                787.50  $         21.00  $                787.50  $           -    $                      -  
606 MGS Bridge Terminal Assembly, Type 1, As Per Plan 4 Each  $    1,905.00  $             7,620.00  $    1,850.00  $             7,400.00  $     1,850.00  $             7,400.00  $           -    $                      -  
606 Anchor Assembly, MGS Type A 2 Each  $    1,210.00  $             2,420.00  $    1,175.00  $             2,350.00  $     1,175.00  $             2,350.00  $           -    $                      -  
606 W-Beam Flared End Section 2 Each  $        52.00  $                104.00  $        50.00  $                100.00  $         50.00  $                100.00  $           -    $                      -  
611 12" Conduit, Type D, As Per Plan 65 LF  $        75.00  $             4,875.00  $        27.00  $             1,755.00  $         75.00  $             4,875.00  $           -    $                      -  
626 Barrier Reflector, Type A2 8 Each  $        10.50  $                  84.00  $        10.00  $                  80.00  $         10.00  $                  80.00  $           -    $                      -  
659 Seeding 5674 SY  $          1.10  $             6,241.40  $          1.10  $             6,241.40  $           2.50  $            14,185.00  $           -    $                      -  
659 Topsoil 15 CY  $        35.00  $                525.00  $      130.00  $             1,950.00  $         25.00  $                375.00  $           -    $                      -  
670 Ditch Erosion Protection Mat, Type B 135 SY  $          3.00  $                405.00  $          3.00  $                405.00  $           3.00  $                405.00  $           -    $                      -  
202 Portions of Structure Removed, As Per Plan 1 Lump  $144,000.00  $          144,000.00  $275,000.00  $          275,000.00  $ 190,000.00  $          190,000.00  $           -    $                      -  
202 Wearing Course Removal 481 SY  $          6.00  $             2,886.00  $          6.00  $             2,886.00  $           4.00  $             1,924.00  $           -    $                      -  
203 Unclassified Excavation 1 Lump  $  45,000.00  $            45,000.00  $  30,000.00  $            30,000.00  $   35,000.00  $            35,000.00  $           -    $                      -  
515 Prestressed Concrete Composite Box Beam Bridge members (CB42-48) Level 1 8 Each  $  41,700.00  $          333,600.00  $  40,000.00  $          320,000.00  $   44,000.00  $          352,000.00  $           -    $                      -  
Special Steel Drip Strip 409 Feet  $        15.50  $             6,339.50  $        18.00  $             7,362.00  $         15.00  $             6,135.00  $           -    $                      -  
704 Splitface Concrete Masonry Block 2048 Each  $        11.00  $            22,528.00  $        16.50  $            33,792.00  $         19.00  $            38,912.00  $           -    $                      -  
704 Solid Concrete Masonry Block 480 Each  $        11.50  $             5,520.00  $        21.50  $            10,320.00  $         22.00  $            10,560.00  $           -    $                      -  
Special High Strength Woven Polyproylene fabric 4000 SY  $          2.90  $            11,600.00  $          4.50  $            18,000.00  $           4.00  $            16,000.00  $           -    $                      -  
203 Granular Embankment #89 Stone 888 Tons  $        49.30  $            43,778.40  $        66.00  $            58,608.00  $         62.00  $            55,056.00  $           -    $                      -  
203 Granular Embankment #304 Stone 454 Tons  $        60.74  $            27,575.96  $        55.00  $            24,970.00  $         34.00  $            15,436.00  $           -    $                      -  
509 Epoxy Coated Reinforcing 30,800 Pounds  $          1.40  $            43,120.00  $          1.85  $            56,980.00  $           1.65  $            50,820.00  $           -    $                      -  
511 Class QC2 Concrete Bridge Deck with QC/QA 156 CY  $    1,081.00  $          168,636.00  $      975.00  $          152,100.00  $       950.00  $          148,200.00  $           -    $                      -  
511 Class QC1 Concrete, Pier 1.5 CY  $  30,000.00  $            45,000.00  $    2,700.00  $             4,050.00  $   10,000.00  $            15,000.00  $           -    $                      -  
511 Class QC5 Concrete, As per plan 6 CY  $      730.00  $             4,380.00  $      725.00  $             4,350.00  $       400.00  $             2,400.00  $           -    $                      -  
517 Railing-Twin Steel Tube Bridge Railing 362.5 Feet  $      270.00  $            97,875.00  $      262.75  $            95,246.88  $       262.75  $            95,246.88  $           -    $                      -  
601 Rock Channel Protection, Type B  20 CY  $      110.00  $             2,200.00  $      200.00  $             4,000.00  $       125.00  $             2,500.00  $           -    $                      -  
832 Erosion Control 1 Each  $    4,000.00  $             4,000.00  $    5,000.00  $             5,000.00  $           1.00  $                   1.00  $           -    $                      -  
832 Storm Water Pollution Prevention Plan 1 Lump  $    2,000.00  $             2,000.00  $    1,550.00  $             1,550.00  $     1,500.00  $             1,500.00  $           -    $                      -  
832 Storm Water Pollution Prevention Inspection 1 Lump  $    6,000.00  $             6,000.00  $    4,200.00  $             4,200.00  $     1,500.00  $             1,500.00  $           -    $                      -  
832 Storm Water Pollution Prevention Inspection Software 1 Lump  $    6,000.00  $             6,000.00  $    5,000.00  $             5,000.00  $     5,000.00  $             5,000.00  $           -    $                      -  
614 Maintaining Traffic 1 Lump  $    6,500.00  $             6,500.00  $    4,500.00  $             4,500.00  $     5,000.00  $             5,000.00  $           -    $                      -  
624 Mobilization 1 Lump  $  80,000.00  $            80,000.00  $  40,000.00  $            40,000.00  $   40,000.00  $            40,000.00  $           -    $                      -  
        Total  $    1,426,559.10 Total  $    1,479,857.28 Total  $    1,447,182.38 Total  NO BID